Moisture in subfloors and drying times

In short

New concrete and screed hold a lot of water. They must be tested and shown to be dry enough before wood flooring is laid.

How to test

  1. Concrete and screed subfloors should be tested with a hygrometer as described in BS 8201 (Annex A). This gives a relative humidity (RH) reading for the subfloor.
  2. Surface pin or pad meters are useful for quick checks but are not a reliable test on their own.
  3. Test in several places, including areas likely to be dampest: near external walls, in corners and in the middle of large areas.
  4. Keep a written record: date, location, reading and who took it.

Typical maximum readings

  • Sand and cement screed or concrete, floating floor (with a damp-proof underlay): 75% RH
  • Sand and cement screed or concrete, glued floor: 65% RH
  • Calcium sulphate (anhydrite) screed: follow the screed manufacturer's figure. It is usually stricter than for cement screed.
  • Any screed with underfloor heating: 65% RH, after the heating has been commissioned
  • Timber subfloors (joists, boards, plywood): moisture content within about 2% of the new flooring

Always check the figure given in the instructions supplied with your flooring and adhesive. If it is stricter, use that figure.

How long does screed take to dry?

A common rule of thumb for traditional sand and cement screed is about 1 day per millimetre of thickness for the first 50 mm, in good drying conditions. Thicker screeds, cold or damp weather and poor ventilation all make it slower. A 75 mm screed can take several months. Drying time is only a guide. The hygrometer test is what counts.

Important

If a subfloor cannot be shown to be dry enough, a suitable surface damp-proof membrane (DPM) must be used, or fitting must wait.

Most wood floor problems are traced back to site conditions, moisture or installation, not the product. Following this guidance and the instructions supplied with your flooring is the best way to avoid them.

Last updated:
23 November 2026

This is general guidance. Always follow the instructions supplied with your flooring. If in doubt, ask your supplier or a qualified fitter before you start.