Heating, humidity and underfloor heating
In short
Heating should be running normally before delivery. Underfloor heating must be commissioned and run before the floor is laid.
All heating
- Run the heating at normal living temperature for at least a few days before delivery so the building settles.
- Avoid sudden changes. Do not use high heat to dry out a building just before fitting.
- Portable gas or paraffin heaters add large amounts of moisture to the air and should not be used.
Underfloor heating
- The heating system must be fully installed, pressure tested and commissioned before the floor is laid.
- Commissioning means bringing the system up gradually (usually by about 5°C a day) to its maximum operating temperature, holding it there for several days, then reducing it gradually. Follow the heating installer's and screed manufacturer's instructions.
- Ask the heating installer for a written commissioning record and keep it.
- The system should have controls that make it impossible for the floor surface to go above 27°C.
- Re-test the screed for moisture after commissioning.
More detail: Underfloor heating: what to check first.
Important
The surface temperature of a wood floor must never exceed 27°C at any point.
Most wood floor problems are traced back to site conditions, moisture or installation, not the product. Following this guidance and the instructions supplied with your flooring is the best way to avoid them.
Last updated:
23 November 2026
This is general guidance. Always follow the instructions supplied with your flooring. If in doubt, ask your supplier or a qualified fitter before you start.