In short

The subfloor must be clean, dry, sound and flat before any wood flooring is laid.

Clean

  • Remove dust, debris, plaster, paint, old adhesive and anything that could stop the floor lying flat or the adhesive bonding.
  • On screeds, any weak, powdery surface layer (laitance) must be removed, especially on calcium sulphate (anhydrite) screeds before gluing.

Dry

  • Test concrete and screed with a hygrometer and keep a record. See Moisture in subfloors and drying times.
  • Timber subfloors should be within about 2% of the moisture content of the new flooring.

Sound

  • The subfloor must be firm, with no movement, bounce or squeaks.
  • Screed must be hard and not crumbling, cracked or hollow.
  • Loose floorboards should be screwed down. Damaged boards should be replaced.
  • There must be no rot, damp or insect damage.

Flat

  • The usual requirement is no more than 3 mm gap under a 2 m straight edge, measured anywhere on the floor. This is surface regularity class SR1 in BS 8204.
  • Check in several directions. Grind down high spots. Fill low spots with a suitable levelling compound.
  • Flat and level are not the same. A floor can slope gently and still be flat. Flatness is what matters most for wood flooring.

Common subfloors

  • Concrete or sand and cement screed: must be fully dry and tested. Use a damp-proof membrane if it cannot be shown to be dry enough.
  • Calcium sulphate (anhydrite) screed: remove surface laitance and prime before gluing. Follow the screed manufacturer's moisture limit. Not compatible with some adhesives.
  • Timber floorboards on joists: must be secure and flat. For glued floors, overlay with plywood first. Floating floors are usually laid at right angles to existing boards.
  • Plywood or chipboard: must be suitable for flooring, secure and flat. Sand swollen edges flat.
  • Existing tiles: must be firmly bonded, clean and flat. Glossy tiles may need preparing before gluing.
  • Joists only (no subfloor): only for products specifically designed to span joists. Most engineered flooring is not. Check the product instructions.
Important

The person fitting the floor is responsible for checking the subfloor is suitable before starting. If it is not, it should be put right first.

Most wood floor problems are traced back to site conditions, moisture or installation, not the product. Following this guidance and the instructions supplied with your flooring is the best way to avoid them.

Last updated:
23 November 2026

This is general guidance. Always follow the instructions supplied with your flooring. If in doubt, ask your supplier or a qualified fitter before you start.